What Drives Make Good Costs in Melbourne
Why two quotes for the same tenancy look so different
Why two quotes for the same tenancy look so different
Two make good quotes land on your desk for the same tenancy. One is half the other. Neither comes with much explanation.
That's the most common call we get from tenants approaching lease end. They want to know what a make good should cost, and why the numbers are all over the place.
There's no honest square metre rate for a make good. Two tenancies of the same size can need completely different work. What we can do is explain what actually moves the price, so you can read a quote properly and give a contractor what they need to price it accurately.
This is general information, not legal or financial advice. Your lease decides what you owe, so read it and get advice on anything unclear.
A make good isn't a product. It's whatever your lease says has to happen, measured against the condition the premises were in when you moved in.
That means the price comes from three things:
A contractor who quotes a rate per square metre over the phone is guessing. Sometimes the guess is close. Often it isn't, and the difference shows up as variations once work starts.
Size matters, but less than most people think. Floor area drives the obvious items:
But a large, simple space can cost less than a small, complicated one. A 2,000 square metre warehouse with bare walls and a sound slab is a lighter job than a 300 square metre office with partitions, a kitchen, comms rooms and a raised floor.
This is the one that swings the price most. The make good is measured against the ingoing condition, so the gap between the two is the scope.
Things that widen the gap:
Things that narrow it:
Without an ingoing report, the scope becomes whatever the landlord's agent says it is. That almost always costs the tenant more. Our guide to dilapidation reports and make good explains why that document matters so much.
Two leases can describe the same tenancy and ask for very different things. The wording drives the scope, and the scope drives the price.
Clauses that change the number:
If your lease gives the landlord a choice, push for that decision in writing as early as you can. A contractor can't give you a firm price for a scope nobody has agreed.
Once the lease and the condition are known, the scope is the list of actual work. Some items carry far more weight than others.
The lighter items:
The heavier items:
Any item that needs a licensed trade, a certificate or specialist equipment adds cost and time. That's not padding. It's the work.
When and how the work happens changes the price as much as what the work is.
Things that push costs up:
Things that bring costs down:
Most budget blowouts come from things nobody saw at quote stage. The usual suspects:
You can't remove every unknown. But a proper site inspection, a look under the floor coverings in a few spots and an asbestos register check before quoting cut the surprises right down.
When two quotes are far apart, it's usually one of these reasons:
| Reason | What it looks like on the quote |
|---|---|
| Different scope | One quote includes items the other left out |
| Assumptions | Lower quote assumes fair wear and tear on items the lease may not allow |
| Exclusions | Asbestos, after hours work or slab repairs listed as excluded |
| Provisional sums | A placeholder amount for unknown work that may increase later |
| Rates versus fixed price | Hourly or daywork pricing that grows with the job |
| Site inspection | One contractor walked the site, the other priced from photos |
| Certificates | One includes electrical certificates and clearances, one doesn't |
The cheaper quote isn't always the cheaper job. Read the exclusions first. That's where the real difference usually sits.
The better the information you give a contractor, the tighter the price. Here's what to have ready.
An engineering firm in the eastern suburbs got two quotes. The lower one excluded slab repairs entirely. Once the machinery came out, the floor had dozens of anchor holes and two cracked bays. The work still had to be done, at variation rates, in the final week.
A professional services tenant in the CBD budgeted for a full strip out. Their lease said the landlord could elect what stayed. The incoming tenant wanted the meeting rooms and kitchen. Once that was agreed in writing, the scope dropped by more than half.
A distribution tenant in the west had no ingoing condition report. The property manager's list included worn line marking, faded paint and old hairline cracks in the slab. Without photos from the start of the lease, the tenant had little to push back with and paid for most of it.
Earlier is cheaper. Not because contractors charge less for early work, but because time gives you options.
With time on your side you can:
We cover the full planning timeline in our guide to strategic make good planning. The short version: start talking to contractors three to six months before your lease ends, not three weeks.
A quote you can rely on is boring to read. It should have:
If you can't match each line on the quote to something in your lease or your condition report, ask why it's there.
Can the landlord just keep my bank guarantee instead? Sometimes. That's a payment in lieu by another name. It can be simpler, but the landlord's own number is rarely lower than a properly scoped quote. Know what the work would cost before you agree.
Can we do some of the work ourselves? Moving furniture, clearing stock and taking down your own signage, yes. Anything that needs a licence, a certificate or a sign off, no. A cheap job that fails the inspection costs more than doing it right once.
Does a bigger quote mean better work? Not by itself. A bigger quote may just carry more risk allowances. What matters is a clear scope, a short list of exclusions and a contractor who has walked the site.
Can the price change once work starts? On a fixed price, only if the scope changes or something genuinely hidden turns up. That's why the exclusions and provisional sums matter so much at quote stage.
Make goods usually involve demolition, electrical, plumbing, ceilings, flooring, painting and cleaning. Getting separate prices for each and lining them up yourself is slow, and gaps between trades are where costs creep in.
Our make good service covers the full scope under one fixed price, from the strip out through to repairs and handover. We inspect the site, check the scope against your lease and condition report and give you a number you can plan around.
Send through the property address and lease timing and we can review the scope. Get in touch.
We do makegoods all day, every day.
Let's talk scope.
Share the details and we'll come back to you with how we can help.
Ask us anything
👋 Hi! How can I help you today?
Ask about our make-good services, areas we cover, or how we can help with your commercial property.